The COMPLETED view shows both complete and incomplete tasks. I just want to see the completed tasks when that view is selected. Any suggestions?
2 Answers
OOTB the COMPLETED view is set to show tasks that have 100% completion percentage. This means that even if a task status says incomplete and have reach 100%, it will show up in the view. This needs to change, since it's not working for your current internal process of task management.
Edit the completed view, in the same section where you select a different view.
In the filtering section, change to filter on status, rather than %completed. Set the filter to only show completed status and make sure that only the completed tasks are filtered as visible. Save and check the result.
-
-
-
I created a new view using the Task status filter but the list still displays all the tasks complete and incomplete. Thank you.– AamirCommented Apr 14, 2015 at 16:29
-
1@aamir One more thing you can try... What happens if you group by status on the default view?– Benny Skogberg ♦Commented Apr 14, 2015 at 17:50
-
1
someone else suggested that this was a bug in Feb 2015 updates and can be worked around by changing the style of the view to anything other than the default. I hope this helps someone