I have a 2013 List Workflow running in SPO. I am copying the date/time field from a calendar list and pasting it in another list. On about half of the operations, it copies the date/time properly. But if the event is labeled "All Day", the workflow consistently subtracts 5 hours from the time. So, if the event started at 12:00 AM 11/14/2017, after copy/pasting it shows as 7:00 PM 11/13/2017. Can anyone tell me why it does this and how to prevent it? I've double checked that the "Start Date" columns for both lists are identical.
1 Answer
Since the workflow consistently subtracts 5 hours from the time, which also changes the date, I simply added an if/then statement that looks at the condition of "All Day Event". If it is yes, I add 5 hours and 1 minute to the time, which changes the date and time back to the original plus 1 minute. Not super elegant, but a fast, consistent solution.