1

For instance, if I have one main task, with 5 subtasks under it....and each of those 5 subtasks has a percent complete filled out.....

I then want the main task to auto-calculate a total percentage complete like it does in a project....is this possible?

1 Answer 1

2

Unfortunately, it's not possible

The roll-up feature that used to auto calculate the overall %Complete is not available in the SharePoint Tasks list.

It's only available in the Project Schedule in Project Server & Microsoft Project.