in project 2010 - calendar working time , why the details button is disabled ?

enter image description here

Thank you

1 Answer 1

0

It's a normal behavior, you should first add your Exceptions as Name, Start and Finish, then select one of your exceptions. thence you will note that the detail button has been activated as shown below.

enter image description here

For more details check Add a resource's vacation/Exceptions time

2
  • Thank you, additional question please? what's your m-project version ? it looks different from my window ? Commented May 1, 2017 at 21:15
  • It's Microsoft Project Prof 2013. but the same steps would work for you in Microsoft Project Prof 2010, could you please mark my answer as answer if it helped you :) Commented May 1, 2017 at 21:17