in project 2010 - calendar working time , why the details button is disabled ?
Thank you
It's a normal behavior, you should first add your Exceptions
as Name, Start and Finish, then select one of your exceptions. thence you will note that the detail button has been activated as shown below.
For more details check Add a resource's vacation/Exceptions time