I'm new in MS project
I want to know what's the difference between percent complete / work complete ?
Thank you
In Microsoft Project and Project server, there are two fields % complete
and %work complete
Both fields refer to the percent of achievements.but the difference is
(Actual Duration / Duration) * 100
(Actual Work / Work) * 100
For example:
You have a project that has one task. this task has duration 7 days that started in 08/04/2017 and today is 11/04/2017 so the percent of achievements based on duration (%Complete) is about 50 % if your plan is on schedule and based on the actual duration.
Meanwhile, the % Work Complete
will depend on actual resources work based on their timesheet and working hour per day for this task.
For more details check