0

I'm new in MS project

I want to know what's the difference between percent complete / work complete ?

Thank you

1 Answer 1

3

In Microsoft Project and Project server, there are two fields % complete and %work complete

Both fields refer to the percent of achievements.but the difference is

  • %Complete field value calculated based on Duration.
    • The equation of % complete is = (Actual Duration / Duration) * 100
  • %Work Complete field value calculated based on Work.
    • The equation of % Work Complete is = (Actual Work / Work) * 100

For example:

You have a project that has one task. this task has duration 7 days that started in 08/04/2017 and today is 11/04/2017 so the percent of achievements based on duration (%Complete) is about 50 % if your plan is on schedule and based on the actual duration.

Meanwhile, the % Work Complete will depend on actual resources work based on their timesheet and working hour per day for this task.

For more details check

2
  • Thank you sir for your answer, i'm muddled between the actual duration and duration definition ? Commented Apr 11, 2017 at 21:19
  • to avoid any type of confusion please check Duration fields at support.office.com/en-us/article/… please don't hesitate to tell me if you need more clarification also, please mark my answer if it helped you :) Commented Apr 11, 2017 at 21:22

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.