Here is an excel formula to calculate number of workdays between two dates:

=IFERROR( IF ( A2 = B2, 0, NETWORKDAYS( A2, B2 ) -1 ), "" )

is it possibe to write this formula in SharePoint List as a calculated column please?

Thanks

1

According to my research, the NETWORKDAYS function can be used in excel, but not for SharePoint.

Please following steps:

1.Create two "Date and Time" column named StartDate and EndDate in list.

enter image description here

2.Then, create one "Calculated" column named Workdays

3.Please use the below Formula:

IF(ISERROR(DATEDIF([StartDate],[EndDate],”d”)),””,(DATEDIF([StartDate],[EndDate],”d”))+1-INT(DATEDIF([StartDate],[EndDate],”d”)/7)*2-IF((WEEKDAY([EndDate])-WEEKDAY([StartDate]))<0,2,0)-IF(OR(AND(WEEKDAY([EndDate])=7,WEEKDAY([StartDate])=7),AND(WEEKDAY([EndDate])=1,WEEKDAY([StartDate])=1)),1,0)-IF(AND(WEEKDAY([StartDate])=1,(WEEKDAY([EndDate])-WEEKDAY([StartDate]))>0),1,0)-IF(AND(NOT(WEEKDAY([StartDate])=7),WEEKDAY([EndDate])=7),1,0))

enter image description here

4.When you enter date, SharePoint will automatically calculated the number of working days between the two dates.

enter image description here