0

I am trying to auto populate a field END DATE as (START DATE + 30 days) in an infopath form which should autopopulate end date in date format. Can anyone help me here. Thank you.

  • Google 3 things, defining variable in infopath, add date formula in infopath, and last auto populate fields in infopath. After that combine it into one. – Utkarsh Dubey May 19 at 12:33
1

It is easy using infopath rules. Add a rule for start date field. Set the condition to be start date is not blank. For actions, add action "set fields's value". Configure it to set the end date to be start date+30 days, just like the screenshot below. The field5 is your end date field. enter image description here

| improve this answer | |
  • Thank you sooo much, Jerry. It helped me! :) – HRY May 20 at 7:32

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy