0

Am facing an performance issue in MS Flow which need to back track dates for 12 columns with business days logic (ignoring weekends) in SharePoint office site. wee have SharePoint list with 12 columns and we need to derive dates on no.of days given another list.This has been achieved using Do While Loop in MS flow which is taking 2mins to execute this logic.

enter image description here

Is there any direct formula for calculating weekdays logic in MS flows? Or Any other approach other than using DO – WHILE loop in MS Flow?.

run time of flow is also not consistent.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Browse other questions tagged or ask your own question.