0

I am looking to pull data from PWA into PowerBI. When I add the Project table in, I don't see the Project field "Priority" This is kind of a key field for us and I don't know where it is.

1 Answer 1

1

I found it. It is in tasks. If you have a row and the TaskIndex = 0 then that contains the projects priority.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.