I have a "Days Past Due" calculated Column and used your calculated formula (link Sharepoint 2013 Custom List Calculate difference between Today and Column Value) and is working fine. But there is another column called [Status] and if value equals "Closed" then it should bring the previous days value. Meaning will freeze the value and will not get changed next day.
Example: Days Past due-> "7 days Past" and Status-> "In Progress" then tomorrow it should increase by one. But if I edit the item tomorrow and set Status-> "Closed" then it should show previous calculated column data which is "7 days Past"
Below is the code I tried but did not get result.
=IF(ISBLANK([Target Completion Date]),"Missing date",
IF(OR(Status="1. Open",Status="2. In Progress"),
"<img src='/_layouts/images/blank.gif'
onload=""{"
& " var SPday=new Date(); "
& " SPday.setFullYear("
& YEAR([Target Completion Date])
& ","
& MONTH([Target Completion Date])-1
& ","&DAY([Target Completion Date])
& ");"
& " var Days=Math.round((SPday.getTime()-new Date().getTime())/86400000);"
& " this.parentNode.innerHTML=Math.abs(Days)+' days '+((Days<0)?'past':'left');"
& "}"">","<img src='/_layouts/images/blank.gif' onload=""{ "
& " var Days=this.parentNode.text();"
& " this.parentNode.innerHTML=Days;"
& "}"">"
)
)
Any help will be appreciated.
Thanks a lot.
&"
starts on a new line so its readable=IF(ISBLANK([Target Completion Date]),"Missing date",IF(OR([Status]="1. Open",[Status]="2. In Progress"),"", "")))