I have a requirement where in I have started a workflow. I have assigned a task and now I do not want to wait for task action.

I want the workflow to end just after the task is created. How do I do that in SharePoint 2013 workflow?

I am working on designer 2013

3

Use Stages. Once you have assigned your task within the workflow, then use the "Transition to Stage" : Go to End of Workflow.