9

I want to create acalculated column that takes a date field and sets the value to the date, increased by one day. How can this be done?

For ex:

If date field value: 20/10/2015 calculated result will be: 21/10/2015

Suggest some formula to use.

  • 2
    =[Date]+1. However it does not update automatically. – Christoffer Oct 12 '15 at 11:25
10

Date columns are essentially numbers starting at 30/12/1899

So besides adding one day, you have to display it as a date again (when using it in a Calculated Column datatype=Text)

=TEXT( [Due Date]+1 , "dd/mm/yyyy" )

Or set the datatype of the Calculated Column to Date

=[Due Date]+1

Adding one day correctly counts the new date

=TEXT(DATE(2015,12,31+1),"dd/mm/yyyy")

outputs january 1st 2016

More Date functions: http://viewmaster365.com/365coach/#/Calculated_Column_Functions_List