Basically, I'm trying to use SharePoint as some what of a project tool for tasks.
On a new task, we have "START DATE", and a custom number field "ETC". I'd like to have a calculated field "END DATE" populated by adding the ETC (estimated time to complete) to the START DATE, but the result should display a date that is within a business work week (Monday through Friday).
i.e.
Start Date = 4/8/2015
ETC = 8 Days
End Date (excluding weekends) = 4/20/2015 (Calculated Field)