0

I have a simple workflow that looks for a date in a list (Target date) and sets the 'Acknowledged Target Date' to 5 days after the 'Received date'. It then creates a task for the Complaints Administrator, once the task is complete it sets 'Complaint date' to 'Today'. See the workflow steps below.

The problem we sometimes have is that the workflow status remains 'In Progress', for a day or two, even though the 'Acknowledged Target Date' is set and the task is completed by the user. This doesn't happen every time.

Set Acknowledged Target Date (workflow) to Target date:5 days

then Start Acknowledge Complaint process on Current Item with Complaint Administrator

then Set Complaint Date (workflow) to Today

1 Answer 1

0

try to end/stop workflow through the actions. though not correct approach but will work.

0

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.