What is the formula to calculate working days between two dates on lists SharePoint? Keeping in mind that the working week here in Dubai is Sunday to Thursday - Fridays and Saturdays are the weekend. Please help. thanks

1 Answer 1

0

You can try this monstrosoty. Replace the date names (FirstDate and SecondDate) and the semicolons with commas if you get an error. This tests for WEEKDAY = 6 and 7 which are fridays and saturdays.

=IF(ISERROR(DATEDIF([D;];[SecondDate];"d"));"";(DATEDIF([FirstDate];[SecondDate];"d"))+1-INT(DATEDIF([FirstDate];[SecondDate];"d")/7)*2-IF((WEEKDAY([SecondDate])-WEEKDAY([FirstDate]))<0;2;0)-IF(OR(AND(WEEKDAY([SecondDate])=6;WEEKDAY([FirstDate])=6);AND(WEEKDAY([SecondDate])=7;WEEKDAY([FirstDate])=7));1;0)-IF(AND(WEEKDAY([FirstDate])=7;(WEEKDAY([SecondDate])-WEEKDAY([FirstDate]))>0);1;0)-IF(AND(NOT(WEEKDAY([FirstDate])=6);WEEKDAY([SecondDate])=6);1;0))

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.