In my "time off" custom list I have start date and end date. I want to make the user splits up the entries if the time off spans months. In other words if the entry starts Oct 25 and ends Nov 5 I want the user to be prompted to make two entries (one with Oct 25-31) and another with Nov 1-5 instead of allowing the span over two months. Thanks for any help on this!

share|improve this question

1 Answer 1

One solution is a workflow that fires when they add a new item, the other is an Event Handler that fires when they add a new item. Workflows can be built using SharePoint Designer and don't necessarily require programming experience; while Event Handlers are built using Visual Studio and requires quite a bit of programming experience. I know this isn't a complete answer, but at least you know what your options are. I don't think there is an OOTB solution for this.

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.