When we start an approval process in a SPD workflow, we can fill in the "duration of the task" and/or the "due date ". But what exactly happens when we cross the date?

A reminder to the person with the task?
The workflow ends?
My laptop explodes?
...

Thanks

link|improve this question

feedback

1 Answer

up vote 1 down vote accepted

Duration per task can be specified in days, weeks, or months. When the unit time is "crossed", an action can be taken (e.g, the task escalated). Here is a detailed example showing a task escalation: Task Escalation using Workflows.