I have created a Project Task List (aka the one with the Gantt Chart) and we are having a problem because no one can edit anything. I have reviewed all the permissions and I can't find anything wrong. I have full control permissions on the list and still I get nothing but that grayed out box saying it is disabled. Anyone got any ideas on how to allow edits to that row of my project task table?enter image description here

share|improve this question
    
how were you able to display the 'person or group' field in gantt chart? –  anonymus Aug 11 at 20:22

1 Answer 1

up vote 1 down vote accepted

I got it figured out. You have to enable the edit column on the project task list. The "edit item" button isn't an option at any time for this list. Instead you add the "edit item" column on the list and it will give you a pencil icon in that column for each entry.

Here is a walk through of how to fix it with screen shots if you need more information on adding the column.

http://ryandunn.co/sharepoint-not-able-to-edit-items-in-a-project-task-gantt-chartenter image description here

share|improve this answer
    
Thank you very much for this post, it helped a lot! –  user9015 Jun 21 '12 at 15:58

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.